TABLE OF CONTENTS

  1. Introduction
     
  2. Overview of the Decision Process
     
    1. The Goal of this Decision Process
    2. Policy Objectives to Guide the Decision
    3. Decision Considerations
       
  3. Review of Alternatives
     
  4. Financial Strategies and Decision Factors
     
    1. Long Range Financial Capabilities
    2. Decision Factors
      1. Cost
      2. Ridership
      3. Schedule
      4. Community Impacts
      5. Long Range Financial Capabilities
      6. Constructability
      7. Operations Feasibility
         
  5. Project Implementation
    1. Risk Assessment
    2. Schedule
    3. Business Plan

 

LIST OF FIGURES

    Figure 1 Cross County Corridor MetroLink Route Segments
    Figure 2 Strategic Alignment Analysis
    Figure 3 Alternative Alignments in Segment I of the CrossCounty
                         Corridor
    Figure 4 Comparative Analysis of Alignments for Initial Screening
    Figure 5 Atgrade Operation In an Urban Center
    Figure 6 Atgrade Operation on Exclusive RightofWay and in
                         MixedTraffic
    Figure 7 Alignment SIA (North of Forest Park)
    Figure 8 Alignment SIB (Through Forest Park)
    Figure 9 Estimated Schedule to Implement CrossCounty MetroLink
                         Expansion

 

LIST OF TABLES

    Table 1 Projected Sources of Funding for MetroLink Expansion:
                         19982015
    Table 2 Performance Measures for SI Unadjusted MTIA Data
    Table 3 Performance Measures for SI Adjusted MTIA Data
    Table 4 Cost Containment Measures Alignment SIA
    Table 5 Cost Containment Measures Alignment SIB
    Table 6 Capital Costs and Outlays for CrossCounty Segment I
                       Alternatives
    Table 7 Capital Costs and Outlays for All CrossCounty Segments
    Table 8 Projected Prop. M Capital Uses for All CrossCounty Segments

     


Strategic Alignment Analysis

GO TO:

TOC

Next

Figures

[Home]  [About Us[Our Region] [Calendar]  [Links]  [Library]  [Site Map]

East-West Gateway Council of Governments
One Memorial Dr., Ste 1600
St. Louis, MO  63102
phone: (314) 421-4220 or (618) 274-2750
   fax: (314) 231-6120
e-mail: webmaster@ewgateway.org

 

last update: Friday, September 01, 2006